The Beginner's Guide to Importing Heavy Machinery from China
The sourcing cycle from initial contact to first shipment typically takes 3-6 months for new products. Month 1: supplier research and initial contact. Month 2: sample development and evaluation. Month 3: negotiation and order placement. Month 4: production (varies by product). Month 5: inspection and shipping. Month 6: delivery and evaluation. Plan your inventory accordingly and don't expect to compress this timeline without cutting corners.
Quality control should not be a single inspection at the end. Build a multi-point QC plan: (1) raw material inspection before production starts, (2) first article inspection when the first unit comes off the line, (3) in-process inspection at 30% and 60% completion, (4) pre-shipment inspection when 80% is packed, (5) container loading supervision. Each step costs a fraction of catching defects at the destination.